How to use the cost report

Navigate to cost reports

  1. Click on Projects on the left-hand menu.
  2. Click on My Projects.
  3. Click the project you want to view.
  4. Click on the Costs tab. (You should be directed here automatically.)

Cost Overview

Your cost overview comprises of a few key metrics that provide an overview of your entire project spend.

Contract ValueThis is the current value of the contract including all variations & BoQ progress updates after the contract has begun.
Tender ValueThis is the original value of the contract.
Contract BudgetThis is the current budget of the contract including all variations & BoQ progress updates after the contract has begun.
Tender BudgetThis is the original budget of the contract before it starts.
Contract MarginThe difference between Contract Value and Contract Budget.
Tender MarginThe difference between Tender Value and Tender Budget
Contract Margin PercentageContract Margin as a percentage of Contract Value.
Tender Margin PercentageTender Margin as a percentage of Tender Value.
Current ValueThe total valuation figure from valuations.
ProgressThis is a progress bar that shows your Current Value relative to your Contract Value.
Actual CostsThe actual amount that has been spent so far on a project.
Actual MarginThe current profit to date on a project.
Actual Margin PercentageThe Actual Margin is a percentage of revenue.
Current BudgetThis the forecast of your budget to date.
Current Budget Margin 
Current Margin Percentage 

Cost Overview Actions

  • Add Costs - Add new cost documents directly from here.
  • Download Summary - Downloads an XLS summary of your costs.
  • Refresh

Cost Report Table

This table appears right under the Cost Overview. It provides an in-depth look at your project financials from a Cost Group perspective. It displays each cost group and shows their respective values.

Cost Report Actions

  • Show/Hide Columns - Click on the Columns button at the top right corner of the table to toggle on/off the metrics you want to see for each cost group.
  • Edit Values - Manually edit the values of your cost report. This is only possible if your BoQ items are.not linked to your costs. Learn More